Skip to main content
Back to Main Project

SSD Modifications

Determination

Powerhouse Parramatta MOD 2 - Height and construction hours

City of Parramatta

Current Status: Determination

Interact with the stages for their names

  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

- increase the height of the western building from RL79.2m to RL 82.35m
- design changes to the rooftop pavilion and part of the level 3 façade of the eastern building
- extend Saturday construction hours from 8am to 1pm to 8am to 5pm

Attachments & Resources

Notice of Exhibition (1)

Modification Application (6)

Response to Submissions (6)

Agency Advice (4)

Additional Information (3)

Determination (4)

Consolidated Consent (1)

Submissions

Filters
Showing 1 - 3 of 3 submissions
City of Parramatta Council
Comment
PARRAMATTA , New South Wales
Message
Attachments
Name Withheld
Comment
Parramatta , New South Wales
Message
I object to the proposed extension of the construction hours to 5 pm on Sat (from the current 1 pm). The noise from this project starts early in the morning 6 days a week. Often residents are unable to sit outside due to the noise and they are unable to carry out a conversation. I think that it is unreasonable to extend the hours to the weekend. I would rather have an additional hour added on during the week. Also, it seems to me that there should be some information as to whether the proposed extended hours will shorten the construction timeline. If so, how much will it be shortened...a month...2 months? Or will it simply get the project back to the original timeline. This is information that residents and the council should be informed of given that their outdoor activities on a non-work day will be disrupted. If it is additional time to increase the height (the other modification to which i do not object) I would be opposed to any extension of the construction time on Sat. I am also concerned about the precedent such an extension of Sat. construction time will set. The CBD is dramatically changing, and we are surrounded by, the noise, dust and inconvenience of construction everyday except the weekend. This will be the state of the area for many years to come based on all the development proposals. Will this Sat. hours extension be given out to other construction site across the CBD? What will the basis be for the Council to reject the next application for extended hours? Construction in the area must consider the fact that the area remains home to thousands of people.
Name Withheld
Support
PARRAMATTA , New South Wales
Message
The changes to the building don't make much of a difference.

I have no objections to the change in construction hours, it is in line with Parramatta's reputation as a CBD and will hopefully stimulate the local economy.

Pagination

Project Details

Application Number
SSD-10416-Mod-2
Main Project
SSD-10416
Assessment Type
SSD Modifications
Development Type
Museum, Gardens & Zoos
Local Government Areas
City of Parramatta
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Thomas Piovesan