Kemps Creek Warehouse, Logistics and Industrial Facilities Hub

Penrith

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Development of a warehouse, logistics and industrial facilities hub including construction and operation of eight warehouses comprising 162,355 m2 of floor space, 744 parking spaces and 21-lot Torrens Title Subdivision (over two stages).

Consolidated Consent

SSD-9522-MOD-3 Consolidated Consent

Archive

Request for SEARs (1)

Scoping Report Appendix 1 - Supporting Information Report

EIS (45)

Appendix 21 - Air Quality Impact Assessment
2018 Ecoplanning letter re EPBC Act
Application_20190528055107
EIS
Appendix 1 - SEARs
Appendix 2 - Quantity Surveyors Report
Appendix 3 - Survey Plan
Appendix 4 - Subdivision Plan
Appendix 5 - Stage 1 SSD Application Plan
Appendix 6 - Architectural Plans
Appendix 7 - Urban Design Report
Appendix 8 - Landscape Plan
Appendix 9 - Visual Impact Assessment Report
Appendix 10 - Civil Plans and Design Report
Appendix 10 - Civil Plans and Design Report Part 1
Appendix 10 - Civil Plans and Design Report Part 2
Appendix 10 - Civil Plans and Design Report Part 3
Appendix 11 - Overland Flow Report
Appendix 11 - Overland Flow Report_1of3
Appendix 11 - Overland Flow Report_2of3
Appendix 12 - Service Infrastructure Assessment
Appendix 13 - Hazards and Risk Assessment
Appendix 14 - Geotechnical Report
Appendix 16 - Phase 2 Contamination Report
Appendix 17 - Site Salinity Assessment Report
Appendix 18 - Traffic Impact Assessment
Appendix 19 - Biodiversity Development Assessment Report
Appendix 20 - Riparian and Groundwater Dependent Ecosystem
Appendix 22 - Economic Impact Assessment
Appendix 23 - Social Impact Assessment
Appendix 24 - Historical Heritage Impact Statement
Appendix 25 - Noise Impact Assessment
Appendix 26 - Archaeological Report
Appendix 27 - Aboriginal Cultural Heritage Assessment
Appendix 27 - ACHAR Checklist
Appendix 28 - Greenhouse Gas Assessment
Appendix 29 - Ecologically Sustainable Development Report
Appendix 30 - Waste Management Plan
Appendix 31 - Bushfire Report
Appendix 32 - Community Consultation Report
Appendix 33 - Agricultural Impact Assessment
Appendix 35 - Sewer Lead-In Advice
Appendix 36 - Strategic Justification Report
Appendix 37 - Architectural Design Report
Appendix 38 - Mamre South Precinct Development Control Plan

Response to Submissions (38)

RTS Planning Report
Clause 55 Amendment Request
Appendix 1 - Consolidated Agency Response to Submissions
Appendix 2 - SSD 9522 DCP 2020
Appendix 3 - QS Report
Appendix 4 - Stage 1 Subdivision Plan
Appendix 5 - Stage 2 Subdivision Plan
Appendix 6 - SSD Application Masterplan
Appendix 7 - Architectural Plans
Appendix 8 - Architectural Design Statement
Appendix 9 - Architectural Design Report
Appendix 10 - Landscape Plans
Appendix 11 - LVIA
Appendix 12 - Civil Engineering
Appendix 13 - Overland Flow Report
Appendix 14 - Service Infrastructure Assessment
Appendix 15 - Hazards and Risk Assessment
Appendix 16 - Traffic Impact Assessment
Appendix 17 - BDAR
Appendix 18 - Air Quality Impact Assessment
Appendix 19 - Noise Impact Assessment
Appendix 20 - CNVMP
Appendix 21 - Historical Heritage Impact Statement
Appendix 22 - Archaeological Report
Appendix 23 - ACHAR
Appendix 24 - Greenhouse Gas Assessment
Appendix 25 - ESD Report
Appendix 26 - Bushfire Assessment Report
Appendix 27 - Groundwater Dependent Aquatic Ecosystem Assessment
Appendix 28 - Building Surveying Letter
Appendix 29 - VPA Letter of Offer Correspondence
Appendix 30 - Sydney Water Correspondence
Appendix 31 - Crown Road Reserve Owner's Consent
Appendix 32 - NSW DPIE Submission
Appendix 33 - Gazette No 36 dated 21 February 2020
Appendix 34 - Swept Path Analysis
Request RTS_19072019_025647
Request for RtS August 2019

Agency Advice (14)

20201030 - TfNSW Concurrence
EES comments on RtS
FRNSW comments on RtS
PCC comments on RtS
TfNSW comments on RtS
WaterNSW comments on RtS
Planning Partnership comments on RtS
Endeavour Energy comments on RtS
Sydney Water comments on RtS
HNSW ACH comments on RtS
EES comments on RtS addendum
GSC comments on RtS addendum
PCC comments on RtS addendum
TfNSW commends on RtS addendum

Additional Information (18)

Request for Information (01/09/2020)
RFI Attachment 2 - Agency comments
Response to Submissions addendum
Appendix 1 - Email Correspondence
Appendix 2 - Masterplan
Appendix 3 - Stage 1 Subdivision Plan
Appendix 4 - Stage 2 Subdivision Plan
Appendix 5 - Swept Paths Analysis_reduced
Appendix 6 - Land Zoning Overlay Plan
Appendix 7 - Landscape Plans
Appendix 8 - Civil Engineering Letter of Support
Appendix 9 - Ecoplanning Letter of Support
Appendix 10 - BDAR Shapefiles
Appendix 11 - Flora and Fauna List
RFI Request for Additional Information_28092020_010500
657-769 Mamre Road, Kemps Creek - Response to S
20201016 - Supplementary Info - Amended Site Plan
20201002 - Supplementary Info - TfNSW

Determination (3)

SSD-9522 Consent
SSD-9522 Notice of Decision
SSD-9522 Assessment Report

Post-determination Notices (1)

SSD-9522 Public Notice of Determination

Approved Documents

Management Plans and Strategies (16)

CEMP
Approval of Plan Strategy or Study_27052022_114142
Biodiversity Management Plan
Approval of Plan Strategy or Study_29102021_103347
34009.CHMP.Mamre.South.Precinct.FIN05.20211012 (1)
App I Cultural Heritage Management Plan
App F Construction Stormwater Management Plan
App E Construction Traffic Management Plan
App G Construction and Demolition Waste Management Plan
App J Unexpected Contamination Procedure
App H Biodiversity Management Plan
App D Construction Air Quality Management Plan
App C Construction Noise and Vibration Management Plan
660.30061-R01-v1.3-20221013 Clean CEMP
App K Community Consultation Strategy
App B Event Notification

Notifications (4)

21003 INSP-RPT-COMP-1-210511
21003 INSP-RPT-COMP-210504
21003 INSP-RPT-COMP-210426
21003 INSP-RPT-COMP-210420

Other Documents (6)

KCW ER - DPIE Approval Letter
Appointment of Experts_01022021_042644
21003 ERMR-06-0-21101
21003. YARDS-LTR-220813
Other_14122021_071008
Turning Paths Plan Set

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

26/07/2022

07/09/2022

20/09/2022

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 18 of 18 submissions
Paul Fittler
Comment
LUDDENHAM , New South Wales
Message
I have a concern that a holistic view is being overlooked, the traffic management report for this application only refers to the impact it alone will create; and the intersection upgrades at a very local area.
Who is considering the the overall traffic management of the combined current and future applications along Mamre Rd and Luddenham Rd, such as the Science park, Raceway, Airport and continued future developments along both these roads.
The intersection of Luddenham Rd and Mamre Rd have issues now!, and yet there is no mention of how this key intersection and roads will be upgraded to handle over 300% increase in the next 5 years.
The Anglican Schools Corporation
Comment
THORNLEIGH , New South Wales
Message
Details provided in the attached letters.
Attachments
Elizabeth Begg
Comment
MOUNT RIVERVIEW , New South Wales
Message
The proposal indicates very large areas of roof surfaces that will replace existing grass and trees. Given the increase of the Urban Heat Sink Effect affecting western Sydney and the concern many local councils and residents in western Sydney and the Blue Mountains feel about increasing urban temperatures, I think green roofs are an appropriate inclusion in this very large warehouse development.
Inclusion of rain gardens to capture stormwater and redirect into planted areas should also be included in this proposal.
Inclusion of plants as green walls on external walls will also increase green cover and the many benefits plants provide such as pollution reduction, stormwater mitigation, cooling of air temperatures, carbon dioxide sequestration and storage, and provision of a healthier (physically and mentally) environment for those accessing this site and those living nearby.
There is so much 'green infrastructure' development in the developed world and Australia should be part of this movement as we do experience very hot summer temperatures.
I think there should be specific justification as to why these sensible features are not included in the proposed development. There is so much research available to support these strategies, and there will be so much money needed to implement strategies retrospectively as built infrastructure increases in western Sydney.
I applaud the revegetation of the riparian area and encourage inclusion of Water Sensitive Urban Design (WSUD) elements and Green Infrastructure strategies in this large development.
This would provide a much prouder development for our state government to present to the people of western Sydney and NSW! I encourage you to please consider my comments and feedback on this proposed development.
With regard
Elizabeth Begg
BSc, DipEd, DipArb
Consultant Arborist
Sustainable Trees Arboriculture
HERITAGE COUNCIL OF NSW
Comment
,
Message
Please refer attached.
Attachments
Transgrid
Comment
Wallgrove , New South Wales
Message
Attachments
NSW Rural Fire Service
Comment
SYDNEY OLYMPIC PARK , New South Wales
Message
Attachments
Fire + Rescue NSW
Comment
Greenacre , New South Wales
Message
Attachments
Greater Sydney Commission
Comment
Parramatta , New South Wales
Message
Attachments
Water NSW
Object
Parramatta , New South Wales
Message
Attachments
Sydney Water
Comment
Parramatta , New South Wales
Message
Attachments
Environment Protection Authority
Comment
Sydney , New South Wales
Message
Attachments
Transport for NSW
Comment
Sydney , New South Wales
Message
Attachments
Environment, Energy and Science Group
Comment
PARRAMATTA , New South Wales
Message
Attachments
BGMG 11 Pty Ltd
Object
KEMPS CREEK , New South Wales
Message
Attachments
Department of Planning, Infrastructure and Environment - Lands, Water and Primary Industries
Comment
Sydney , New South Wales
Message
Attachments
Penrith City Council
Object
PENRITH , New South Wales
Message
Attachments
Roads & Maritime Services
Comment
Parramatta , New South Wales
Message
Attachments

Pagination

Project Details

Application Number
SSD-9522
Assessment Type
State Significant Development
Development Type
Warehouse or distribution centres
Local Government Areas
Penrith
Decision
Approved
Determination Date
Decider
Executive Director
Last Modified By
SSD-9522-Mod-3
Last Modified On
29/09/2022

Contact Planner

Name
Bianca Thornton