Stormwater Outlet Upgrade - Narrawallee Beach - Victor Avenue, Narrawallee

Shoalhaven

The proposed activity is the upgrade of the stormwater outlet and outflow onto Narrawallee Beach.
The purpose of the proposed activity is to reduce the erosion of the beach escarpment currently occurring below the existing outlet. The outlet was assessed as high risk for asset damage. If the erosion is not abated, civil infrastructure could become exposed and become vulnerable to damage. This infrastructure includes the public road (Victor Avenue) and nearby gravity and pressure rising sewer mains.
The proposed activity includes:
• demolition of the existing headwall and replacement with junction pit,
• installation of flexible stormwater pipe of approximately 16 metres in length from the newly installed junction pit to the sandstone rock platform at the beach,
• installation of a stacked rock outlet headwall
• associated earthworks and sewer protection works
• earthen filling and stabilisation through erosion control and revegetation
Access woudl be from Victor and Surfers Ave.

Review of Environmental Factors (REF) (1)

The approved project is described in the REF, as modified by any associated decision statement (see supporting documents).
Review of Environmental Factors
Review of Environmental Factors REF - stormwater outlet upgrade - Narrawallee Beach - Victor Avenue Narrawallee
Date : Tue, 26/03/2024 - 12:25

Activity Details

Reference number
P5-2024-30
Proponent(s)
Shoalhaven City Council
Address
Narrawallee Beach Off Victor Avenue
Legislation
TISEPP (State Environmental Planning Policy (Transport & Infrastructure) 2021)
Activity Type
Stormwater management systems
Decision
Approved
Determination date