Part 5 Activities
Alteration of Stormwater Drainage System 2B Parson Street, Ulladulla
Shoalhaven
The proposed activity is the diversion of the stormwater management system within Lot 7 SP 75314, 2B Parson Street, Ulladulla. Physical works would involve:
• the demolition of the existing 900 mm reinforced concrete pipe (RCP) – approximately 25 metres in length
• installation of new 1050 mm RCP within a new drainage easement within Lot CP (7) – approximately 25 metres in length
• replacement of RCP with 600 mm RCP – approximately 20 metres in length
• installation and/or reconstruction of stormwater pits to facilitate the proposed diversions
• associated earthworks
• change in use from parking area to parking area and stormwater management
• removal of five trees from the adjacent Shoalhaven City Council managed Crown Land reserve (Lot 7012 DP 1031353).