State Significant Development

Determination

Warwick Farm Printing Facility

Liverpool City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Assessment
  6. Recommendation
  7. Determination

Modifications

Determination
Determination
Determination

Archive

Request for DGRS (1)

Application (3)

EA (29)

Response to Submissions (4)

Determination (2)

Approved Documents

There are no post approval documents available

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

Official Caution issued to Ovato Limited (MP08_0088) Liverpool City LGA

On 10 February 2022, the Department issued an Official Caution to Ovato Limited for failure to prepare and implement an Air Emissions Validation Program and submit to the then Director-General (now Planning Secretary) for approval within three months of commencement of operation of the Warwick Farm Printing Facility as required by the conditions of consent. Preparation and implementation of the Air Emissions Validation Program was required to validate predictions in the Environmental Assessment and compare monitored levels to project emission concentration limit.

Penalty Notice issued to Ovato Limited (MP08_0088) Liverpool City LGA

On 10 February 2022, the Department issued a $15,000 Penalty Notice to Ovato Limited for failure to commission an Independent Environmental Audit (IEA) of the Warwick Farm Printing Facility as required by the conditions of consent. Independent Audits are an independent and objective assessment of the environmental performance and compliance status of a project and are a vital tool in the Department’s risk-based regulation approach. Ovato Limited has since submitted the required IEA.

Official Caution issued to Ovato Limited (MP08_0088) Liverpool City LGA

On 10 February 2022, the Department issued an Official Caution to Ovato Limited for failure to prepare and submit to the then Director-General (Secretary) a Noise Compliance Validation Assessment Report within three months of commencement of operation of the Warwick Farm Printing Facility as required by the conditions of consent. The Noise Compliance Validation Assessment Report was required to compare site noise levels against approved limits and propose additional measures should non-compliances with the approved noise limits be detected. Ovato Limited commissioned a noise monitoring study in November 2021 to rectify the breach.

Penalty Notice issued to Ovato Limited (MP08_0088) Liverpool City LGA

On 10 February 2022, the Department issued a $15,000 Penalty Notice to Ovato Limited for failure to operate within the limits of MP08_0088 as modified (the approval) by operating seven Heat Set Web Offset (HSWO) printers on site, when the approval permitted only six. No environmental assessment was made for the seventh printer, or its potential to add to the cumulative impact of the site. The project has been directed to cease use of the seventh printer. A Modification application has been submitted for the use of the seventh printer, and the Department will continue to monitor and liaise with the project pending the determination.

Inspections

10/02/2022

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Project Details

Application Number
MP08_0088
Assessment Type
State Significant Development
Development Type
Other manufacturing
Local Government Areas
Liverpool City
Decision
Approved
Determination Date
Decider
Minister
Last Modified By
MP08_0088-Mod-4
Last Modified On
14/12/2011

Contact Planner

Name
Megan Webb