State Significant Development

Determination

Dendrobium Mine Extension Project

Wollongong City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Proposed extension to the Dendrobium Coal Mine.
Link to the Independent Planning Commission's page for the Project
https://www.ipcn.nsw.gov.au/cases/2020/10/dendrobium-extension-project-…

Attachments & Resources

Request for SEARs (1)

SEARs (2)

EIS (47)

Response to Submissions (3)

Agency Advice (14)

Amendments (2)

Additional Information (12)

Recommendation (7)

Determination (3)

Approved Documents

There are no post approval documents available

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

There are no inspections for this project.

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 181 - 200 of 775 submissions
Alison Smith
Object
WOLLONGONG , New South Wales
Message
The proposed mine expansion threatens the water supply for Sydney and the Illawarra. Cracking and subsidence have already been observed from existing mining activities, and this has affected rivers, creeks, water courses and swamps. Not only are these waterways and wetlands unique and important habitats, they are also critical to the way that the water catchment works for the benefit of the 5 million people living in Sydney and the Illawarra. South 32 have shown again and again that they have underestimated damage to the catchment caused by mining. Ask any Australian, what is more precious to you, water or coal? The other glaringly obvious issue is that, in order to avoid catastrophic climate change, we must not expand coal mines or open new coal mines. We know that globally, energy markets are moving away from coal-fired power, and we know that the steel industry is working hard on research and development that will allow sustainable production. There are four strong arguments agains this mine expansion, that it threatens drinking water, the it threatens unique habitat, that it takes further down the road to catastrophic climate change, and that it is an investment in a dying industry, a waste of resources that could be used to invest in activity that provides sustainable economic activity. The Independent Expert Panel for Mining in the Catchment has pointed out that we are at risk of losing millions of litres of drinking water per day as the result of this mining company's activities. Australians understand how precious water is. We never take our water supply for granted. And we take it very seriously when business and government fail to protect our precious drinking water.
Rosie Simmons
Object
WOONONA , New South Wales
Message
I object to the Illawarra Coal’s Proposed Mine Extension for Dendrobium. Project SSD-8194.

The Dendrobium Mine Extension Project proposes 30 years of longwall mining in the water catchment for Wollongong, Macarthur and Sydney. It will result in damage and loss of water to swamps, water courses and the Avon, Cordeaux and Nepean Reservoirs[i]. Sydney is the only city in the world that allows longwall mining in a publicly owned water catchment. The proposed mining is in the protected “Special Areas” of the water catchment upon which 5 million people rely for drinking water. We are in drought, paying for desalinated water and our dam levels are below 50% and yet the Dendrobium proposal has the highest water loss of any mine operating in the Greater Sydney Water Catchment area.

- This project is not in the public interest; it is in the wrong place at the wrong time. It would be reckless and immoral for the Department of Planning to support this expansion.
- The proposal will result in significant quantities of greenhouse gas emissions.
- The proposal is estimated to create up to 23.7 million tonnes of CO2e in the production stage and 237 million tonnes in the transport and consumption of the coal produced. This brings the total emissions to between 256 million and 260.7 million tonnes of CO2e for the life of the project[ii].
- The current climate emergency means it is no longer morally acceptable for the NSW government to support projects that will severely negatively impact its capacity to meet greenhouse gas reduction targets. The Rocky Hill case supported climate responsibility in its judgement against the Rocky Hill mine, citing the mining SEPP Clause 14 (2): “... the consent authority must consider an assessment of the greenhouse gas emissions (including downstream emissions) of the development.”[iii]
- To put the volume of emissions in context, the federal government estimates Australia’s greenhouse gas emissions for the year to December 2018 as 538.2 million tonnes[iv]. Thus approval of this mine would lock in emissions over the life of the project the equivalent of 48% of the 2018 annual emissions for all of Australia.
- Annually it would add an average of 8.69 million tonnes per annum (260.7 million tonnes over 30 years) of CO2e to the atmosphere[v]. This is comparable to 1.6% of Australia’s current annual emissions.

South 32’s brinkmanship should not compromise public interest
- South 32 has said that if this proposal is not approved, it will spell the end for the Port Kembla Steelworks and the Port Kembla Coal Terminal. This is misleading and unhelpful to understanding the public interest in relation to this coal mine.
- There are still 11 years of mining at Dendrobium under current approvals (for area 3A and 3B) and South 32 operates other coal mines in the region. South 32 is only selling one third of Dendrobium’s coal to BHP for use in Port Kembla Steelworks. It is exporting the other two thirds.
- Bluescope Steel’s Port Kembla steelworks declined to confirm that the steelworks would collapse if the proposed Dendrobium expansion does not go ahead[vi], so we have to question the truth and motivation for this brinkmanship.

30 year’s of mining is too long

South 32 is seeking approval for 30 years of mining at Dendrobium. This is far too long. Increasing population pressure on water resources and impacts of climate change mean that it would be reckless and irresponsible for the New South Wales Department of Planning to support a 30 year approval.

South 32 has not provided alternatives to this aggressive and destructive mining proposal
The proposal comprises an aggressive plan for twenty one 305 meter wide longwall panels over 30 years. It provides no alternatives to this destructive proposal, a proposal which poses unacceptable risks to the Greater Sydney Water Catchment Special Areas. Offsets do not compensate for mining-induced destruction of catchment land and ecosystems.

South 32‘s proposal to offset catchment land and ecological communities that have been irreparably damaged by mining is not in the public interest; truly like-for-like offsets are rare. Furthermore, there is no “equivalent” land that could compensate for damaged and compromised water catchment. Mining induced subsidence will damage the watercourses and swamps that feed our drinking water reservoirs. South 32 predicts that it’s 305 meter wide long wall panels may result in subsidence of 2m to 2.45m[vii]. Previous mines of similar width have caused 2.5m to 3 m of subsidence, so South 32’s prediction may be conservative[viii].

The mining and associated subsidence will also cause cracking of the land on the surface – including rivers, creeks, smaller watercourses and swamps that feed our drinking water reservoirs – and subsequent water loss to the catchment. No level of damage is acceptable to the Special Areas. It would be immoral for the NSW Department of planning to support this level of destruction in Greater Sydney’s water catchment.



Billions of litres of water will be lost from Greater Sydney’s Water Catchment

The proposed mining is just 300m from Avon Reservoir and 630m from Cordeaux Reservoir[ix]. The mining will cause loss of water from water courses and swamps that feed the reservoirs.

Water loss from the catchment due to Dendrobium’s mining will increase over the coming years, with surface water loss expected to peak at 27.6 ML per day in the year 2035[x]. Consultants estimate that up to 9,500 Megalitres[xi] (ML – million litres) of surface and ground water will flow into the mines each year, which is the equivalent to the annual water usage of 123,940 residents of Greater Sydney[xii].



We ask that you reject this application from Illawarra Coal and commence a process to close the mine at Dendrobium permanently.



Thank you for considering this submission.



Regards,

Rosie Simmons



References

[i] Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[ii] Environmental Assessment Part 2, Section 6, pp 150 – 151 accessed at:

https://www.planningportal.nsw.gov.au/major-projects/project/9696

[iii] Gloucester Resources Limited v Minister for Planning [2019] NSWLEC 7, Item 491, accessed at:
https://www.caselaw.nsw.gov.au/decision/5c59012ce4b02a5a800be47f#_Toc431203

[iv] http://www.environment.gov.au/climate-change/climate-science-data/greenhouse-gas-measurement/publications/quarterly-update-australias-nggi-dec-2018

[v] Environmental Assessment Part 2, Section 6, pp 150 – 151, op cit

[vi] https://www.illawarramercury.com.au/story/6295531/bluescope-wont-say-dendrobium-closure-could-finish-steelworks/

[vii] Subsidence Report for Dendrobium Mine, MSEC, 2019, pp 35 – 37, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[viii] Ibid

[ix] Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[x] Surface Water Assessment, HEC, 2019, p ix, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[xi] ibid, p 111

[xii] Based on an average daily water usage for Sydney residents of 210 litres. Source:
https://theconversation.com/why-sydney-residents-use-30-more-water-per-day-than-melburnians-117656
Name Withheld
Support
BARRACK HEIGHTS , New South Wales
Message
I am in support of the mine extension as it will create many new jobs as well as sure up existing jobs. Also the mining industry is vital to the Illawarra region and supports many other industries both directly and indirectly.
Craig Bowen
Support
THERESA PARK , New South Wales
Message
Benefits all government bodies locally, state and nationally.
Provides a future workplace within Illawarra for thousands of families both directly and indirectly.
Coal from Dendrobium Mine is some of the best in the world. The country needs to utilise our resources that we have.
The setbacks from water courses and bodies are strictly followed.
Adam Roots
Support
PORT KEMBLA , New South Wales
Message
the company is a responsible employer with great community focus.
Name Withheld
Object
PUTTY , New South Wales
Message
I object to the proposed extension to the Dendrobium Coal Mine because it will add to global emissions and therefore climate change. No new coal mines. NSW needs to transition to renewable energy and other export industries to have a stable economy in the future.
Name Withheld
Object
Gordon , New South Wales
Message
I object to the Illawarra Coal’s Proposed Mine Extension for Dendrobium. Project SSD-8194.


The Dendrobium Mine Extension Project proposes 30 years of longwall mining in the water catchment for Wollongong, Macarthur and Sydney. It will result in damage and loss of water to swamps, water courses and the Avon, Cordeaux and Nepean Reservoirs[i]. Sydney is the only city in the world that allows longwall mining in a publicly owned water catchment. The proposed mining is in the protected “Special Areas” of the water catchment upon which 5 million people rely for drinking water. We are in drought, paying for desalinated water and our dam levels are below 50% and yet the Dendrobium proposal has the highest water loss of any mine operating in the Greater Sydney Water Catchment area.

This project is not in the public interest; it is in the wrong place at the wrong time. It would be reckless and immoral for the Department of Planning to support this expansion.

The proposal will result in significant quantities of greenhouse gas emissions

The proposal is estimated to create up to 23.7 million tonnes of CO2e in the production stage and 237 million tonnes in the transport and consumption of the coal produced. This brings the total emissions to between 256 million and 260.7 million tonnes of CO2e for the life of the project[ii].

The current climate emergency means it is no longer morally acceptable for the NSW government to support projects that will severely negatively impact its capacity to meet greenhouse gas reduction targets. The Rocky Hill case supported climate responsibility in its judgement against the Rocky Hill mine, citing the mining SEPP Clause 14 (2): “... the consent authority must consider an assessment of the greenhouse gas emissions (including downstream emissions) of the development.”[iii]

To put the volume of emissions in context, the federal government estimates Australia’s greenhouse gas emissions for the year to December 2018 as 538.2 million tonnes[iv]. Thus approval of this mine would lock in emissions over the life of the project the equivalent of 48% of the 2018 annual emissions for all of Australia.

Annually it would add an average of 8.69 million tonnes per annum (260.7 million tonnes over 30 years) of CO2e to the atmosphere[v]. This is comparable to 1.6% of Australia’s current annual emissions.




South 32’s brinkmanship should not compromise public interest

South 32 has said that if this proposal is not approved, it will spell the end for the Port Kembla Steelworks and the Port Kembla Coal Terminal. This is misleading and unhelpful to understanding the public interest in relation to this coal mine.

There are still 11 years of mining at Dendrobium under current approvals (for area 3A and 3B) and South 32 operates other coal mines in the region. South 32 is only selling one third of Dendrobium’s coal to BHP for use in Port Kembla Steelworks. It is exporting the other two thirds.

Bluescope Steel’s Port Kembla steelworks declined to confirm that the steelworks would collapse if the proposed Dendrobium expansion does not go ahead[vi], so we have to question the truth and motivation for this brinkmanship.



30 year’s of mining is too long

South 32 is seeking approval for 30 years of mining at Dendrobium. This is far too long. Increasing population pressure on water resources and impacts of climate change mean that it would be reckless and irresponsible for the New South Wales Department of Planning to support a 30 year approval.



South 32 has not provided alternatives to this aggressive and destructive mining proposal

The proposal comprises an aggressive plan for twenty one 305 meter wide longwall panels over 30 years. It provides no alternatives to this destructive proposal, a proposal which poses unacceptable risks to the Greater Sydney Water Catchment Special Areas.



Offsets do not compensate for mining-induced destruction of catchment land and ecosystems

South 32‘s proposal to offset catchment land and ecological communities that have been irreparably damaged by mining is not in the public interest; truly like-for-like offsets are rare. Furthermore, there is no “equivalent” land that could compensate for damaged and compromised water catchment.



Mining induced subsidence will damage the watercourses and swamps that feed our drinking water reservoirs

South 32 predicts that it’s 305 meter wide long wall panels may result in subsidence of 2m to 2.45m[vii]. Previous mines of similar width have caused 2.5m to 3 m of subsidence, so South 32’s prediction may be conservative[viii].

The mining and associated subsidence will also cause cracking of the land on the surface – including rivers, creeks, smaller watercourses and swamps that feed our drinking water reservoirs – and subsequent water loss to the catchment.

No level of damage is acceptable to the Special Areas. It would be immoral for the NSW Department of planning to support this level of destruction in Greater Sydney’s water catchment.



Billions of litres of water will be lost from Greater Sydney’s Water Catchment

The proposed mining is just 300m from Avon Reservoir and 630m from Cordeaux Reservoir[ix]. The mining will cause loss of water from water courses and swamps that feed the reservoirs.

Water loss from the catchment due to Dendrobium’s mining will increase over the coming years, with surface water loss expected to peak at 27.6 ML per day in the year 2035[x].

Consultants estimate that up to 9,500 Megalitres[xi] (ML – million litres) of surface and ground water will flow into the mines each year, which is the equivalent to the annual water usage of 123,940 residents of Greater Sydney[xii].

We ask that you reject this application from Illawarra Coal and commence a process to close the mine at Dendrobium permanently.

Thank you for considering this submission.


Regards
Winnie Fu
Object
KENSINGTON , New South Wales
Message
I object to the Illawarra Coal’s Proposed Mine Extension for Dendrobium. Project SSD-8194.

While this submission may have be similar, it has been edited to reflect my personal views as a resident of Sydney.

The Dendrobium Mine Extension Project proposes 30 years of longwall mining in the water catchment for Wollongong, Macarthur and Sydney. It will result in damage and loss of water to swamps, water courses and the Avon, Cordeaux and Nepean Reservoirs . Sydney is the only city in the world that allows longwall mining in a publicly owned water catchment. The proposed mining is in the protected “Special Areas” of the water catchment upon which 5 million people rely for drinking water. We are in drought, paying for desalinated water and our dam levels are below 50% and yet the Dendrobium proposal has the highest water loss of any mine operating in the Greater Sydney Water Catchment area.

This project is not in the public interest; it is in the wrong place at the wrong time. It would be reckless and immoral for the Department of Planning to support this expansion.

The proposal will result in significant quantities of greenhouse gas emissions
• The proposal is estimated to create up to 23.7 million tonnes of CO2e in the production stage and 237 million tonnes in the transport and consumption of the coal produced. This brings the total emissions to between 256 million and 260.7 million tonnes of CO2e for the life of the project .
• The current climate emergency means it is no longer morally acceptable for the NSW government to support projects that will severely negatively impact its capacity to meet greenhouse gas reduction targets. The Rocky Hill case supported climate responsibility in its judgement against the Rocky Hill mine, citing the mining SEPP Clause 14 (2): “... the consent authority must consider an assessment of the greenhouse gas emissions (including downstream emissions) of the development.”
• To put the volume of emissions in context, the federal government estimates Australia’s greenhouse gas emissions for the year to December 2018 as 538.2 million tonnes . Thus approval of this mine would lock in emissions over the life of the project the equivalent of 48% of the 2018 annual emissions for all of Australia.
• Annually it would add an average of 8.69 million tonnes per annum (260.7 million tonnes over 30 years) of CO2e to the atmosphere . This is comparable to 1.6% of Australia’s current annual emissions.



Offsets do not compensate for mining-induced destruction of catchment land and ecosystems
• South 32‘s proposal to offset catchment land and ecological communities that have been irreparably damaged by mining is not in the public interest; truly like-for-like offsets are rare. Furthermore, there is no “equivalent” land that could compensate for damaged and compromised water catchment.
The location of this mine is such that it is not possible to offset another piece of land to mitigate damage so close to the dam. This is a permanent loss of catchment area and pristine land that is impossible to 'offset'.

Mining induced subsidence will damage the watercourses and swamps that feed our drinking water reservoirs
• South 32 predicts that it’s 305 meter wide long wall panels may result in subsidence of 2m to 2.45m . Previous mines of similar width have caused 2.5m to 3 m of subsidence, so South 32’s prediction may be conservative .
• The mining and associated subsidence will also cause cracking of the land on the surface – including rivers, creeks, smaller watercourses and swamps that feed our drinking water reservoirs – and subsequent water loss to the catchment.
• No level of damage is acceptable to the Special Areas. It would be immoral for the NSW Department of planning to support this level of destruction in Greater Sydney’s water catchment.

Billions of litres of water will be lost from Greater Sydney’s Water Catchment
• The proposed mining is just 300m from Avon Reservoir and 630m from Cordeaux Reservoir . The mining will cause loss of water from water courses and swamps that feed the reservoirs.
• Water loss from the catchment due to Dendrobium’s mining will increase over the coming years, with surface water loss expected to peak at 27.6 ML per day in the year 2035 .
• Consultants estimate that up to 9,500 Megalitres (ML – million litres) of surface and ground water will flow into the mines each year, which is the equivalent to the annual water usage of 123,940 residents of Greater Sydney .

South 32’s brinkmanship should not compromise public interest
• South 32 has said that if this proposal is not approved, it will spell the end for the Port Kembla Steelworks and the Port Kembla Coal Terminal. This is misleading and unhelpful to understanding the public interest in relation to this coal mine.
• There are still 11 years of mining at Dendrobium under current approvals (for area 3A and 3B) and South 32 operates other coal mines in the region. South 32 is only selling one third of Dendrobium’s coal to BHP for use in Port Kembla Steelworks. It is exporting the other two thirds.
• Bluescope Steel’s Port Kembla steelworks declined to confirm that the steelworks would collapse if the proposed Dendrobium expansion does not go ahead , so we have to question the truth and motivation for this brinkmanship.

30 year’s of mining is too long
• South 32 is seeking approval for 30 years of mining at Dendrobium. This is far too long. Increasing population pressure on water resources and impacts of climate change mean that it would be reckless and irresponsible for the New South Wales Department of Planning to support a 30 year approval.

South 32 has not provided alternatives to this aggressive and destructive mining proposal
• The proposal comprises an aggressive plan for twenty one 305 meter wide longwall panels over 30 years. It provides no alternatives to this destructive proposal, a proposal which poses unacceptable risks to the Greater Sydney Water Catchment Special Areas.


I ask that you reject this application from Illawarra Coal and commence a process to close the mine at Dendrobium permanently.

Thank you for considering this submission.

Regards
Winnie Fu

Figure sources:
Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696
Environmental Assessment Part 2, Section 6, pp 150 – 151 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696
Gloucester Resources Limited v Minister for Planning [2019] NSWLEC 7, Item 491, accessed at:
https://www.caselaw.nsw.gov.au/decision/5c59012ce4b02a5a800be47f#_Toc431203
http://www.environment.gov.au/climate-change/climate-science-data/greenhouse-gas-measurement/publications/quarterly-update-australias-nggi-dec-2018
Environmental Assessment Part 2, Section 6, pp 150 – 151, op cit
https://www.illawarramercury.com.au/story/6295531/bluescope-wont-say-dendrobium-closure-could-finish-steelworks/
Subsidence Report for Dendrobium Mine, MSEC, 2019, pp 35 – 37, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696
Ibid
Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696
Surface Water Assessment, HEC, 2019, p ix, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696
ibid, p 111
Based on an average daily water usage for Sydney residents of 210 litres. Source:
https://theconversation.com/why-sydney-residents-use-30-more-water-per-day-than-melburnians-117656
William Holliday
Object
LILYFIELD , New South Wales
Message
Mining in this area has resulted in loss of surface water and cessation of creek flows leading to reduction of inflow to dams which are used for water supply. Mining should not occur in this area.
Sue Abbott
Object
MOOBI , New South Wales
Message
Illawarra Coal’s Proposed Mine Extension for Dendrobium:

I object to the Illawarra Coal’s Proposed Mine Extension for Dendrobium. Project SSD-8194.

The Dendrobium Mine Extension Project proposes 30 years of longwall mining in the water catchment for Wollongong, Macarthur and Sydney. It will result in damage and loss of water to swamps, water courses and the Avon, Cordeaux and Nepean Reservoirs[i]. Sydney is the only city in the world that allows longwall mining in a publicly owned water catchment. The proposed mining is in the protected “Special Areas” of the water catchment upon which 5 million people rely for drinking water. We are in drought, paying for desalinated water and our dam levels are below 50% and yet the Dendrobium proposal has the highest water loss of any mine operating in the Greater Sydney Water Catchment area.

This project is not in the public interest; it is in the wrong place at the wrong time. It would be reckless and immoral for the Department of Planning to support this expansion.

The proposal will result in significant quantities of greenhouse gas emissions

The proposal is estimated to create up to 23.7 million tonnes of CO2e in the production stage and 237 million tonnes in the transport and consumption of the coal produced. This brings the total emissions to between 256 million and 260.7 million tonnes of CO2e for the life of the project[ii].

The current climate emergency means it is no longer morally acceptable for the NSW government to support projects that will severely negatively impact its capacity to meet greenhouse gas reduction targets. The Rocky Hill case supported climate responsibility in its judgement against the Rocky Hill mine, citing the mining SEPP Clause 14 (2): “... the consent authority must consider an assessment of the greenhouse gas emissions (including downstream emissions) of the development.”[iii]

To put the volume of emissions in context, the federal government estimates Australia’s greenhouse gas emissions for the year to December 2018 as 538.2 million tonnes[iv]. Thus approval of this mine would lock in emissions over the life of the project the equivalent of 48% of the 2018 annual emissions for all of Australia.

Annually it would add an average of 8.69 million tonnes per annum (260.7 million tonnes over 30 years) of CO2e to the atmosphere[v]. This is comparable to 1.6% of Australia’s current annual emissions.

South 32’s brinkmanship should not compromise public interest

South 32 has said that if this proposal is not approved, it will spell the end for the Port Kembla Steelworks and the Port Kembla Coal Terminal. This is misleading and unhelpful to understanding the public interest in relation to this coal mine.

There are still 11 years of mining at Dendrobium under current approvals (for area 3A and 3B) and South 32 operates other coal mines in the region. South 32 is only selling one third of Dendrobium’s coal to BHP for use in Port Kembla Steelworks. It is exporting the other two thirds.

Bluescope Steel’s Port Kembla steelworks declined to confirm that the steelworks would collapse if the proposed Dendrobium expansion does not go ahead[vi], so we have to question the truth and motivation for this brinkmanship.

30 year’s of mining is too long

South 32 is seeking approval for 30 years of mining at Dendrobium. This is far too long. Increasing population pressure on water resources and impacts of climate change mean that it would be reckless and irresponsible for the New South Wales Department of Planning to support a 30 year approval.

South 32 has not provided alternatives to this aggressive and destructive mining proposal

The proposal comprises an aggressive plan for twenty one 305 meter wide longwall panels over 30 years. It provides no alternatives to this destructive proposal, a proposal which poses unacceptable risks to the Greater Sydney Water Catchment Special Areas.

Offsets do not compensate for mining-induced destruction of catchment land and ecosystems

South 32‘s proposal to offset catchment land and ecological communities that have been irreparably damaged by mining is not in the public interest; truly like-for-like offsets are rare. Furthermore, there is no “equivalent” land that could compensate for damaged and compromised water catchment.

Mining induced subsidence will damage the watercourses and swamps that feed our drinking water reservoirs

South 32 predicts that it’s 305 meter wide long wall panels may result in subsidence of 2m to 2.45m[vii]. Previous mines of similar width have caused 2.5m to 3 m of subsidence, so South 32’s prediction may be conservative[viii].

The mining and associated subsidence will also cause cracking of the land on the surface – including rivers, creeks, smaller watercourses and swamps that feed our drinking water reservoirs – and subsequent water loss to the catchment.

No level of damage is acceptable to the Special Areas. It would be immoral for the NSW Department of planning to support this level of destruction in Greater Sydney’s water catchment.

Billions of litres of water will be lost from Greater Sydney’s Water Catchment

The proposed mining is just 300m from Avon Reservoir and 630m from Cordeaux Reservoir[ix]. The mining will cause loss of water from water courses and swamps that feed the reservoirs.

Water loss from the catchment due to Dendrobium’s mining will increase over the coming years, with surface water loss expected to peak at 27.6 ML per day in the year 2035[x].

Consultants estimate that up to 9,500 Megalitres[xi] (ML – million litres) of surface and ground water will flow into the mines each year, which is the equivalent to the annual water usage of 123,940 residents of Greater Sydney[xii].

We ask that you reject this application from Illawarra Coal and commence a process to close the mine at Dendrobium permanently.

Thank you for considering this submission.

Regards
Sue Abbott
A concerned Earth Protector and Harriet's grandmother

References

[i] Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[ii] Environmental Assessment Part 2, Section 6, pp 150 – 151 accessed at:

https://www.planningportal.nsw.gov.au/major-projects/project/9696

[iii] Gloucester Resources Limited v Minister for Planning [2019] NSWLEC 7, Item 491, accessed at:
https://www.caselaw.nsw.gov.au/decision/5c59012ce4b02a5a800be47f#_Toc431203

[iv] http://www.environment.gov.au/climate-change/climate-science-data/greenhouse-gas-measurement/publications/quarterly-update-australias-nggi-dec-2018

[v] Environmental Assessment Part 2, Section 6, pp 150 – 151, op cit

[vi] https://www.illawarramercury.com.au/story/6295531/bluescope-wont-say-dendrobium-closure-could-finish-steelworks/

[vii] Subsidence Report for Dendrobium Mine, MSEC, 2019, pp 35 – 37, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[viii] Ibid

[ix] Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[x] Surface Water Assessment, HEC, 2019, p ix, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[xi] ibid, p 111

[xii] Based on an average daily water usage for Sydney residents of 210 litres. Source:
https://theconversation.com/why-sydney-residents-use-30-more-water-per-day-than-melburnians-117656
Beverley Atkinson
Object
SCONE , New South Wales
Message
My plane flew yesterday over the Dendrobium site area. I could see the array of dams holding what is left of Sydney's water storage currently. I had a clear view of the naked banks of the several dams in the catchment, and the less than half-full stocks of water, with a dry spring and scorching summer ahead.

Government needs to operate on a Wartime footing in view of the emergency which faces us all; not to further empty the catchments of usable water for the growing population, to please the rich lobbyists and gain quick money. For the sake of the continued life and health of Sydneysiders, full protection from mining should now be put in place. That would apply even if water were the only loss; but the loss extends to the geology which, undamaged, would restore the water supplies. The loss extends to the shading and root-reinforcement of the banks of the catchments. It extends to habitat and biodiversity, but of course Government has no interest in that.

Water and air are our basic requirements, whereas energy and steel are entirely secondary.
But even if steel were essential to life, Dendrobium's coal yield is only one third used for Wollongong. That means that if the remainder is stockpiled for steel instead of sold for cash, the Dendrobium mine need not be extended for steel production. That is the course the Government should now take: Do not extend this mining life, but retain its present yield until end of life, for the steel. By that time, our transfer to sustainable energy production will be well under way. People will be using less, building less, restoring and preserving more, just to survive, at a lower level. The pipedream of growing wealth and luxury is limited to the well paid; but even they will have to pay growing water bills if Dendrobium is allowed to put another hole in our tank.

So say no, retain the existing coal yield for steel, and switch to Wartime footing in order to prolong life here for our children.
Thankyou.
Name Withheld
Support
KANAHOOKA , New South Wales
Message
I support expansion project creating ongoing jobs in region and supplying coal for steelmaking to support ongoing steel production at Port Kembla
Name Withheld
Support
BULLI , New South Wales
Message
Reasons for my support are as follows:
Socio-Economic Benefits
Continued mining would sustain the employment of Dendrobium’s workforce, create a further 100 jobs for the life of the Project and an additional 200 jobs in construction.
The Project will generate around $714 million in royalties, taxes and rates, contributing to local and state infrastructure and services.
The Project will result in a total net benefit to the NSW economy of over $2.8 billion (real, undiscounted terms), including over $1.1 billion (real, undiscounted terms) to the Greater Wollongong Region.
The Project would allow South32 to continue to support local suppliers and contractors, providing additional security and longevity of employment in the region.
The Project would provide an ongoing and essential local supply of metallurgical coal to BlueScope Steelworks. South32 currently supplies around 60% of BlueScope Steelworks’ metallurgical coal requirements.
If approval of the project is not forthcoming, one of the main economic threads of our community will cease having a massive impact on the economic wellbeing of the region, not to mention my family and friends.
If the project is not approved, and coal in the Illawarra dies, then PKCT and the steelworks probably wont be far behind.
The National strategic importance of Port Kembla Steelworks (one of only two of australias steelworks) and the coal industry that underpins it cannot be understated in the current uncertain times.
Please ensure the project is approved and the economic lifeblood of the Illawarra continues to support our families.
Name Withheld
Support
ALBION PARK RAIL , New South Wales
Message
I am an employee of South32 working at Dendrobium Mine Site. I support the project due to the economic benefit the project will provide to the local community and the NSW economy. A large number of people rely on employment associated with the mine; including direct employees, contractors working onsite and a large number of local businesses that support mining activities. The local and state economy benefits greatly from the mine. The Dendrobium Mine Extension Project will allow this economic benefit to continue. The Steelworks will also be significanlty impacted if South32 was unable to continue to provide coal.
Jessica Young
Support
FARMBOROUGH HEIGHTS , New South Wales
Message
I support the coal for steel extension of underground workings within the approved mine lease. This mine provides support to the community and is responsible in its methods and compliance reporting. The mine operates using highest standards and is a leader in safe underground coal mining in NSW. The ongoing financial benefits for the workers, Illawarra businesses, local community and NSW on a whole is significant and must remain.
Name Withheld
Object
GORDON , New South Wales
Message
Dear Ministers and Decision Makers
I object to creating new coal mines because we're currently on track to warm the planet by 4-6% by the end of this century which is a mere 80 years away. Even the 2% target increase is considered dangerous. More than this will probably mean the death of most life on the planet. Our children's lives will be severely, adversely affected.
Australia is the driest country on the planet, and is currently having major fires, which started seasons early, in late winter. 90% of NSW is currently in drought, at the start of spring! Climate change needs action NOW! We need to put 100% of our effort into renewable energy. We have stacks of it (unlike Europe, who are way ahead of us). Even China is way ahead of us in switching to solar power and electric cars. We need to get with the program and become a leader in this vital transformation, which also presents a huge opportunity for smart businesses. There are new industries to be exploited, from using waste to generate power and make recycled building materials to small scale wind (think windmill on every house). And we need to ditch our outdated, 19th century reliance on dirty, polluting coal.
Additionally, this mine puts water supplies at risk. At a time when water is becoming scarcer, this is madness. Most dams, rivers and water supplies are already dangerously low.
Show real leadership and stop putting our kid’s future at risk.
Our school and university kids are marching for action on Climate Change this Friday. Show them you give a damn and reject this mine without hesitation.
Name Withheld
Object
PASCOE VALE SOUTH , Victoria
Message
Illawarra Coal’s Proposed Mine Extension for Dendrobium:

I object to the Illawarra Coal’s Proposed Mine Extension for Dendrobium. Project SSD-8194.

The Dendrobium Mine Extension Project proposes 30 years of longwall mining in the water catchment for Wollongong, Macarthur and Sydney. It will result in damage and loss of water to swamps, water courses and the Avon, Cordeaux and Nepean Reservoirs[i]. Sydney is the only city in the world that allows longwall mining in a publicly owned water catchment. The proposed mining is in the protected “Special Areas” of the water catchment upon which 5 million people rely for drinking water. We are in drought, paying for desalinated water and our dam levels are below 50% and yet the Dendrobium proposal has the highest water loss of any mine operating in the Greater Sydney Water Catchment area.

This project is not in the public interest; it is in the wrong place at the wrong time. It would be reckless and immoral for the Department of Planning to support this expansion.

The proposal will result in significant quantities of greenhouse gas emissions

The proposal is estimated to create up to 23.7 million tonnes of CO2e in the production stage and 237 million tonnes in the transport and consumption of the coal produced. This brings the total emissions to between 256 million and 260.7 million tonnes of CO2e for the life of the project[ii].

The current climate emergency means it is no longer morally acceptable for the NSW government to support projects that will severely negatively impact its capacity to meet greenhouse gas reduction targets. The Rocky Hill case supported climate responsibility in its judgement against the Rocky Hill mine, citing the mining SEPP Clause 14 (2): “... the consent authority must consider an assessment of the greenhouse gas emissions (including downstream emissions) of the development.”[iii]

To put the volume of emissions in context, the federal government estimates Australia’s greenhouse gas emissions for the year to December 2018 as 538.2 million tonnes[iv]. Thus approval of this mine would lock in emissions over the life of the project the equivalent of 48% of the 2018 annual emissions for all of Australia.

Annually it would add an average of 8.69 million tonnes per annum (260.7 million tonnes over 30 years) of CO2e to the atmosphere[v]. This is comparable to 1.6% of Australia’s current annual emissions.




South 32’s brinkmanship should not compromise public interest

South 32 has said that if this proposal is not approved, it will spell the end for the Port Kembla Steelworks and the Port Kembla Coal Terminal. This is misleading and unhelpful to understanding the public interest in relation to this coal mine.

There are still 11 years of mining at Dendrobium under current approvals (for area 3A and 3B) and South 32 operates other coal mines in the region. South 32 is only selling one third of Dendrobium’s coal to BHP for use in Port Kembla Steelworks. It is exporting the other two thirds.

Bluescope Steel’s Port Kembla steelworks declined to confirm that the steelworks would collapse if the proposed Dendrobium expansion does not go ahead[vi], so we have to question the truth and motivation for this brinkmanship.



30 year’s of mining is too long

South 32 is seeking approval for 30 years of mining at Dendrobium. This is far too long. Increasing population pressure on water resources and impacts of climate change mean that it would be reckless and irresponsible for the New South Wales Department of Planning to support a 30 year approval.



South 32 has not provided alternatives to this aggressive and destructive mining proposal

The proposal comprises an aggressive plan for twenty one 305 meter wide longwall panels over 30 years. It provides no alternatives to this destructive proposal, a proposal which poses unacceptable risks to the Greater Sydney Water Catchment Special Areas.



Offsets do not compensate for mining-induced destruction of catchment land and ecosystems

South 32‘s proposal to offset catchment land and ecological communities that have been irreparably damaged by mining is not in the public interest; truly like-for-like offsets are rare. Furthermore, there is no “equivalent” land that could compensate for damaged and compromised water catchment.



Mining induced subsidence will damage the watercourses and swamps that feed our drinking water reservoirs

South 32 predicts that it’s 305 meter wide long wall panels may result in subsidence of 2m to 2.45m[vii]. Previous mines of similar width have caused 2.5m to 3 m of subsidence, so South 32’s prediction may be conservative[viii].

The mining and associated subsidence will also cause cracking of the land on the surface – including rivers, creeks, smaller watercourses and swamps that feed our drinking water reservoirs – and subsequent water loss to the catchment.

No level of damage is acceptable to the Special Areas. It would be immoral for the NSW Department of planning to support this level of destruction in Greater Sydney’s water catchment.



Billions of litres of water will be lost from Greater Sydney’s Water Catchment

The proposed mining is just 300m from Avon Reservoir and 630m from Cordeaux Reservoir[ix]. The mining will cause loss of water from water courses and swamps that feed the reservoirs.

Water loss from the catchment due to Dendrobium’s mining will increase over the coming years, with surface water loss expected to peak at 27.6 ML per day in the year 2035[x].

Consultants estimate that up to 9,500 Megalitres[xi] (ML – million litres) of surface and ground water will flow into the mines each year, which is the equivalent to the annual water usage of 123,940 residents of Greater Sydney[xii].



We ask that you reject this application from Illawarra Coal and commence a process to close the mine at Dendrobium permanently.



Thank you for considering this submission.



Regards



References

[i] Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[ii] Environmental Assessment Part 2, Section 6, pp 150 – 151 accessed at:

https://www.planningportal.nsw.gov.au/major-projects/project/9696

[iii] Gloucester Resources Limited v Minister for Planning [2019] NSWLEC 7, Item 491, accessed at:
https://www.caselaw.nsw.gov.au/decision/5c59012ce4b02a5a800be47f#_Toc431203

[iv] http://www.environment.gov.au/climate-change/climate-science-data/greenhouse-gas-measurement/publications/quarterly-update-australias-nggi-dec-2018

[v] Environmental Assessment Part 2, Section 6, pp 150 – 151, op cit

[vi] https://www.illawarramercury.com.au/story/6295531/bluescope-wont-say-dendrobium-closure-could-finish-steelworks/

[vii] Subsidence Report for Dendrobium Mine, MSEC, 2019, pp 35 – 37, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[viii] Ibid

[ix] Dendrobium Mine – Plan for the Future: Coal for Steelmaking, Groundwater Assessment for South32 – Illawarra Coal, NPM Technical Pty Ltd trading as HydroSimulations, 2019, p 101 accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[x] Surface Water Assessment, HEC, 2019, p ix, accessed at:
https://www.planningportal.nsw.gov.au/major-projects/project/9696

[xi] ibid, p 111

[xii] Based on an average daily water usage for Sydney residents of 210 litres. Source:
https://theconversation.com/why-sydney-residents-use-30-more-water-per-day-than-melburnians-117656
Name Withheld
Object
STRATHFIELD , New South Wales
Message
I object to the extension or expansion of any mine that poses any risk to the water supply of Sydney.
Our water storage is at low enough levels now to warrant water restrictions on the residents of Sydney. Consultants estimate that up to 9,500 Megalitres (ML – million litres) of surface and ground water will flow into the mines each year, which is the equivalent to the annual water usage of 123,940 residents of Greater Sydney.

I ask that you reject this application from Illawarra Coal and commence a process to close the mine at Dendrobium permanently.
Illawarra Residents for Responsible Mining Inc
Object
CORRIMAL , New South Wales
Message
Please see submission attached.
Attachments
Name Withheld
Object
SOUTH TURRAMURRA , New South Wales
Message
The use of fossil fuels such as coal is causing massive environmental problems. I object to any expansion of coal mining and would like the whole industry closed down to try and mitigate the dire consequences of increased Carbon Dioxide in the atmosphere. I fear the short term allure of money is unfortunately more motivating than the health of the planet, it's like I'm on Easter Island watching my neighbor sharpening an axe, preparing to cut down the last tree.

Pagination

Project Details

Application Number
SSD-8194
EPBC ID Number
2017/7855
Assessment Type
State Significant Development
Development Type
Coal Mining
Local Government Areas
Wollongong City
Decision
Refused
Determination Date
Decider
IPC-N

Contact Planner

Name
Elle Clémentine