Skip to main content

State Significant Development

Determination

New Primary School at Gregory Hills

Camden

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Construction of a new primary school comprising one and three storey buildings, outdoor play spaces, parking and associated works.

Consolidated Consent

Consolidated Conditions

Archive

Notice of Exhibition (1)

Request for SEARs (1)

SEARs (4)

EIS (34)

Response to Submissions (20)

Agency Advice (11)

Additional Information (6)

Determination (4)

Approved Documents

Management Plans and Strategies (1)

Independent Reviews and Audits (1)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

18/07/2023

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 3 of 3 submissions
Name Withheld
Comment
GREGORY HILLS , New South Wales
Message
Hi,
I've gone through the Architectural Plans, Design Report and the Infrastructure report (Elect & Comms) published/attached with the exhibition notice. There are couple of things that I want to bring to your notice that have a significant impact on the existing housing opposite to the proposed school building.

1. All of the mechanical plants/plant rooms, 1000 KVA electric substation, hydraulic/water pumping stations, waste pad, utilities service room have been designed to be located in one single direction, directly opposite to exiting housing on Long Reef Cct. These mechanical/ electrical /waste management utilities generate a significant noise and other environmental pollutions and will have a direct impact on the residents of exiting housing on Long Reef Cct. The structures built for these utilities are also not very visually appealing.
The site is surrounded by 2 large open spaces (one towards Gregory Hills drive and other towards Howard park) . These utilities can be located towards that direction which will significantly reduce any environmental and visual impact on housing on Long Reef Cct.

2. Apart from the location of these utilities which are directly opposite to Long Reef Cct, the short stay parking is also being built on Long Reef Cct. This road is already very narrow and adding a short stay parking on this road will increase the congestion on this particular road.

Looks like the proposed design has no consideration for the residents living on this side of Long Reef Cct. Every supporting infrastructure (electrical/comms/pumping station/waste removal/road usage) has been cramped into one particular direction of a narrow Long Reef Cct street. Request the planners/designers to have some thought around it and have some consideration towards the residents living on this street.
Camden Council
Comment
Oran Park , New South Wales
Message
Attachments

Pagination

Project Details

Application Number
SSD-41306367
Assessment Type
State Significant Development
Development Type
Educational establishments
Local Government Areas
Camden
Decision
Approved
Determination Date
Decider
Director
Last Modified By
SSD-41306367-Mod-2
Last Modified On
07/03/2024

Contact Planner

Name
Bethany Lane