  1. Prepare Mod Report
  2. Assessment
  3. Recommendation
  4. Determination

Amendment to the construction methodology involving the building up of a sediment capping layer and work platform within the coffer dam beneath the approved basement for the new Sydney Fish Market.

Attachments & Resources

Modification Application (9)

Agency Advice (6)

Additional Information (1)

Determination (3)

Consolidated Consent (1)

Project Details

Application Number
SSD-8925-Mod-7
Main Project
SSD-8925
Assessment Type
SSD Modifications
Development Type
Marinas
Local Government Areas
City of Sydney
Decision
Approved
Determination Date
Decider
Team Leader

Contact Planner

Name
Lucinda Craig