MOD 1 - Substation and further geotechnical investigations

Snowy Monaro Regional

Current Status: Determination

Interact with the stages for their names

  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

1. Additional borehole drilling and geophysical surveys;
2. Establishment of a construction power connection to TransGrid 330kV line 2 at Lobs Hole; and
3. Changes to project boundary for constructability and additional infrastructure

Attachments & Resources

Modification Application (2)

Response to Submissions (19)

Determination (3)

Consolidated Approval (1)

Submissions

Filters
Showing 1 - 12 of 12 submissions
Comment
SYDNEY , New South Wales
Message
Attachments
George Thomas
Object
LAKE ALBERT , New South Wales
Message
While I accept Snowy 2.0 has merit there are aspects of the project that are not in the public interest.
My report is attached
Attachments
The Colong Foundation for Wilderness
Object
SYDNEY , New South Wales
Message
Attachments
Gary Bilton
Object
TALBINGO , New South Wales
Message
Attachments
HERITAGE COUNCIL OF NSW
Comment
,
Message
Please refer attached.
Attachments
Environment Protection Authority
Comment
QUEANBEYAN , New South Wales
Message
Attachments
Roads & Maritime Services (Maritime)
Comment
PORT KEMBLA , New South Wales
Message
Attachments
Department of Planning, Industry & Environment (Biodiversity and Conservation)
Comment
QUEANBEYAN , New South Wales
Message
Attachments
DEPARTMENT OF INDUSTRY
Comment
,
Message
Please see attached formal response from the Department of Planning, Industry and Environment - Crown Lands & Water, and Department of Primary Industries for the above matter.
Please note that this was emailed through to Anthony Ko on 11 July 2019.
Attachments
Roads and Maritime Services
Comment
WOLLONGONG , New South Wales
Message
Attachments
ROADS AND MARITIME SERVICES
Comment
,
Message
RMS response sent 24/07/19
Attachments
National Parks Association of NSW
Object
PYRMONT ,
Message
Submissions attached
Attachments

Pagination

Project Details

Application Number
SSI-9208-Mod-1
Main Project
SSI-9208
Assessment Type
SSI Modifications
Development Type
Electricity generation - Other
Local Government Areas
Snowy Monaro Regional
Decision
Approved
Determination Date
Decider
Executive Director

Contact Planner

Name
Anthony Ko