Skip to main content
Back to Main Project

SSD Modifications

Determination

MOD 1 - Building R4B Design Changes

City of Sydney

Current Status: Determination

Interact with the stages for their names

  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

• Reduce no. of apartments from 297 to 283
• Revised dwelling mix & internal layout refinements
• Facade & landscaping alterations
• Reduction in height by 1.7 m
• Addition of 20 residential car spaces and removal of 1 retail car space

Attachments & Resources

Modification Application (12)

Response to Submissions (4)

Agency Advice (1)

Additional Information (7)

Recommendation (2)

Determination (4)

Submissions

Filters
Showing 1 - 5 of 5 submissions
ENVIRONMENT PROTECTION AUTHORITY
Comment
Sydney , New South Wales
Message
Hi Karl,
Please find attached the EPA's comments on Barangaroo - R4B Residential Building - MOD 1 - Building R4B Design Changes (SSD-6965-Mod-1).
Kind regards,
Mark Hanemann
Attachments
TRANSPORT FOR NSW
Comment
Chippendale , New South Wales
Message
A copy of the TfNSW letter is attached.
Attachments
ROADS AND MARITIME SERVICES DIVISION
Support
PARRAMATTA , New South Wales
Message
No objections.
Attachments
City of Sydney
Object
SYDNEY , New South Wales
Message
Hi Karl

Please see the City's letter to SSD 6964, which relates to SSD 6965.

Regards

David
David and Lorraine Sketch
Comment
MILLERS POINT , New South Wales
Message
Modification Application R4A (SSD6964-Mod-1) and R4B (SSD6965-Mod-1)
Thank you for your notification dated 29 October 2019 regarding the proposed modifications.
While we have had limited time to review all details of each modification, in principal we have no objections.
We note that the Development Consents for Building R4A and Building R4B dated 7 September 2017 (Part D During Construction) limits the hours of construction to between 7am and 7pm, Mondays to Fridays and 7am and 5pm Saturdays.
We again implore the Department to ensure that the approved hours of construction are adhered to and that any allowed works undertaken outside these hours use low-noise equipment, noise reduction barriers, curtains and attenuating devices to minimise disturbances to the community.
We have for the second time this year suffered sleep deprivation because of overnight low frequency noise from the use of de-watering pumps on the One Sydney Harbour site.

David and Lorraine Sketch

Pagination

Project Details

Application Number
SSD-6965-Mod-1
Main Project
SSD-6965
Assessment Type
SSD Modifications
Development Type
Residential & Commercial
Local Government Areas
City of Sydney
Decision
Approved
Determination Date
Decider
Executive Director

Contact Planner

Name
Karl Fetterplace