Skip to main content

State Significant Development

Determination

Kemps Creek Data Centre

Penrith

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Construction and Operation of a Data Centre including two data storage buildings, 61 generators, substation, high voltage switch yard, 30 diesel storage tanks, office, internal access roads and landscaping.

Attachments & Resources

Notice of Exhibition (1)

Request for SEARs (6)

SEARs (1)

EIS (30)

Response to Submissions (10)

Agency Advice (40)

Additional Information (2)

Determination (3)

Approved Documents

Management Plans and Strategies (9)

Reports (4)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

25/07/2023

31/10/2023

14/11/2023

15/11/2023

20/02/2024

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 1 of 1 submissions
Penrith City Council
Comment
,
Message
Good Afternoon,

Please find attached response from Kathryn Saunders, Principal Planner in response to Kemps Creek Data Centre.

Kind regards
Simone Muscat
Secretary - Management Team
Attachments

Pagination

Project Details

Application Number
SSD-10101987
Assessment Type
State Significant Development
Development Type
Warehouse or distribution centres
Local Government Areas
Penrith
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Shaun Williams