Bass Point Quarry (MOD 3) - Amenity barriers

Shellharbour City

Current Status: Determination

Interact with the stages for their names

  1. Prepare Mod Report
  2. Exhibition
  3. Collate Submissions
  4. Response to Submissions
  5. Assessment
  6. Recommendation
  7. Determination

Amendment to Location of Amenity Barriers

Attachments & Resources

Notice of Exhibition (1)

Uncategorised (1)

Response to Submissions (2)

Agency Advice (13)

Additional Information (6)

Determination (3)

Consolidated Consent (1)

Submissions

Filters
Showing 1 - 5 of 5 submissions
Vicki Steele
Object
MINNAMURRA , New South Wales
Message
Attention: Carl Dumbleton
Please confirm receipt of this submission.
Thank You
Vicki
Attachments
Australand Corporation (NSW) Pty Ltd
Comment
SHELL COVE , New South Wales
Message
BASS POINT QUARRY PROJECT APPROVAL 08_0143 MODIFICATION 3
On review of the proposed application to modify Project Approval (PA) 08143, Australand would like to seek consideration that the application includes the importation of other fill material classified with a resource recovery order and exemption as approved by the Environmental Protection Authority (EPA).
The restriction of incorporating the importation of only Virgin Excavated Natural Material (VENM) and/or Excavated Natural Material (ENM) for use in landscaping and progressive rehabilitation at the Quarry may place unnecessary restrictions on material well suited for the proposed use, however does not meet the explicit criterial of the VENM and/or ENM resource recovery order and exemption.
Australand believes further consideration should be given to broadening the permissible material classifications for importation to the site for the following reasons:
1. There is currently significant construction activity within the Shell Cove and broader Shellharbour LGA which will likely result in the need for exportation of excavated material over time. Inherent within the local geology of the area are naturally elevated levels of copper marginally exceeding the ENM resource recovery order and exemption. Classification restrictions outlined within a planning consent does not give consideration for the EPA to consider the stability of such fill material based on merit and could exclude an appropriate reuse consideration for material not suited in other application or restricted by other planning consents.
2. In consideration of the above, broadening of permissible importation materials will allow excess fill material to be disposed of locally. The ability to source suitable fill sites for material that has received a classification other than VENM or ENM is difficult in the Illawarra region. An additional fill site consideration such as the Quarry could assist in reducing unnecessarily truck travel lengths, road use and noise generation through local communities and arterial road networks without adversely impacting the geological characteristics of the locality.
3. Further to these considerations, disposal of material that does not meet the VENM and/or ENM resource recovery order and exemption has a risk of placing unnecessary burden on the resources and capacity of licensed waste facilities.
Australand considers that the Modification Report and subsequent modified Consent could be suitably addressed through the inclusion of wording such as ‘or other material approved by the EPA’ where reference is made to VENM and/or ENM. This terminology is common within Consents approved by Shellharbour City Council (and other Councils) where applicable to the attributes of the site. We consider that the robust assessment therefore undertaken by the EPA would give the appropriate consideration necessary to ensure the material is suitable for reuse within the locations proposed at the Quarry.
Attachments
Leslie Brooks
Object
SHELL COVE , New South Wales
Message
Hanson Construction Materials Modification Report Mod 3 Bass Point Quarry
Report Number 706/05

12 January 2022
Submission on behalf of

Leslie Brooks
66 Killalea Drive, Shell Cove
CCC Member Hanson Bass Point
[email protected]

I am a current member of the Hanson Bass Point Quarry Community Consultative Committee (CCC) and I represent community concerns in my submission to this amendment.

In this submission I am objecting to the proposed amendment on the basis that the importing of VENM/ENM will create an unwanted dust impact and the construction of the visual amenities will have a minimal benefit to blocking off quarry activities for the wider community.

The Modification request is an outcome from a Development Control Order (the Order) served to Hanson by the Department of Planning, Industry and Environment and dated 4 February 2021. The Order refers to non-compliance with Condition 2 of Schedule 2 of PA 08_0143, that is, the need for development to occur in accordance with the EA for the Project.

My objection to the proposed amendment Mod 3 is based on concerns that the scope of the project does not clearly explain how the proposed amendment relates to the remediation work subject to Development Control Order served to Hanson by the Department of Planning, Industry and Environment and dated 4 February 2021.

The Order refers to non-compliance with Condition 2 of Schedule 2 of PA 08_0143, that is, the need for development to occur in accordance with the EA for the Project.

A further reason for my objection is because the Modification document (Bass Point Quarry Modification 3 PA 08_0143) which is open for public comment does not clearly show where visual amenity construction will occur, other relevant details (location/volume/quantity) regarding the materials to be imported to the quarry are missing from the main document.

The visual amenity barriers are for most practical purposes are completed and throughout the construction process to date there was a significant dust impact. Since 2018 to present 17% of complaints recorded in Hanson Bass Point Complaint Register were related to dust complaints.

On 6th January 2022 a collaborative discussion with Hanson (Steve Butcher and Chelsea Flood) with myself and other CCC members was held, this discussion also included a tour of the facility to view the locations where visual amenity construction is required.

I have also included 2 draft diagrams showing missing details, for accuracy and clarity these diagrams need to be reviewed and updated by Hanson, I am requesting that relative diagrams to be included in the final version of the modification proposal.


My concerns and requirements of this modification proposal are summarised below.

The visual amenities to be modified or constructed are not clearly detailed in the modification proposal. I am requesting the approval document to be revised to include a diagram that clearly shows existing visual amenities vs the proposed visual amenities, the diagram needs to allow the general public to understand the locations where the visual amenities will be constructed or modified. Refer to the attached diagram as an example to clearly show the proposed work of the visual amenities to be constructed.

------------ refer to attachment for diagram A

For the purpose of the development consent, Hanson propose that no more than 200,000tpa of VENM or ENM material would be imported each calendar year. My first concern on this matter is that the volume of VENM/ENM that is required to construct the required visual amenities has not been identified. Section 2.3.1 Importation Campaigns and Limits of the modification proposal should include an engineering estimate the volume of VENM/ENM required to meet the requirements of the control order.

My second concern is that the modification requesting approval to import 200,000tpa per calendar year has no termination date. If the modification is approved then the import of materials in theory could occur for the next 20years or longer.

The project should provide an estimate of VENM.ENM volume that will allow the control order to be finalised and based on historical records it should be possible to estimate and include a targeted termination date such that the import of 200,000tpa will be within a defined time frame.

The materials to be imported are currently stockpiled in an area adjacent to the quarry. For the purpose of clarity, the transport / haul route will be quite direct. The approved document should show the proposed transport / haul route to be used for the relocation of the stockpiled VENM/ENM. As further comment, because the materials will be transported using specific mining haulage trucks with an estimated load capacity of 50 tons, the transport of 200,000 tpa gives an estimated volume at approximately 4,000 trucks per year.

------------ refer to attachment for diagram B

It is my understanding that the visual amenities will be constructed by Frasers who are managing construction activities at the Shellharbour Marina. I am requesting that the EPA ensure that a timeline for the project to be determined with possible allowances for issues out of control (ie: Covid health order closures). The benefits of a controlled and reduced timeline will be dust generated from the project will have a reduced impact, rather than generating dust over a longer and protracted timeline.

Historically while the Marina has been under construction the cause of dust impacting the nearby community of Shell Cove has been difficult to isolate as dust has been generated by both quarry activities and by Marina construction activities. With the majority of Marina work completed the modification on the quarry site should hold Hanson responsible for any dust complaints, otherwise it will be impractical to hold either Hanson nor Frasers as the responsible agents for dust control.

In my opinion the benefits of the control order are not clearly understood and the largest impact of not enforcing the control order would be the management of the stockpiled material from land which is owned by Shellharbour council. Apart from possible impact to the views from the south and the remediation of the visual amenity the visual impacts on the north eastern boundary would have little benefits for the community.

In this objection to the modification proposal, the EPA must consider if the control order should be revoked or reviewed with the intent to remediate the southern boundary visual amenity.
Attachments
Shellharbour City Council
Comment
Shellharbour , New South Wales
Message
Please refer attachment
Attachments
Shellharbour City Council
Comment
SHELLHARBOUR CITY C+ , New South Wales
Message
Comments were provided to Carl by Jessica Saunders on 20 January 2022.

Pagination

Project Details

Application Number
MP08_0143-Mod-3
Main Project
MP08_0143
Assessment Type
SSD Modifications
Development Type
Extractive industries
Local Government Areas
Shellharbour City
Decision
Approved
Determination Date
Decider
Director

Contact Planner

Name
Jarrod Blane